Previous Item Print Next Item

January 14, 2021 City Council Meeting
Title
20. Authorize the City Manager to Execute a Final Project Closeout Amendment for the Holly Heights Park Development Contract with Johnson-Laux in the Amount of $15,048.15 ( Event No. 7287)
Strategic Priority
Good Government
Description

Recommend approval of a Final Project Closeout Amendment in the amount of $15,048.15 to Johnson Laux Construction Company for additional work performed as part of the Holly Heights Park development.

The original contract for this project included the construction of a new full-sized basketball court, stormwater infrastructure upgrades, playground and landscaping.    

The amendment is required due to additional scope of services which included additional grading, installation of 12-foot fencing around perimeter of basketball court and additional stormwater upgrades necessary to complete the project.

The original contract was approved by City Council on August 1, 2019 in the amount of $347,355.29.  The total contract amount to date including this modification is $362,403.43.

S.S.         Johnson-Laux Construction (Savannah, GA)(A)      $15,048.15

A) Indicates local, DBE business

Recommendation

Approval

Contact
Cristy Lawrence, Director of Capital Projects Management
Financial Impact
Expenditure of $15,048.15 from the Capital Improvement Fund
Review Comments
Attachments
Exhibit 1: Purchasing Summary - Holly Heights Park Development Amendment.docx
Exhibit 2: Funding Verification - Holly Heights Park Development Amendment.pdf