Title 16. Authorize the City Manager to Execute a Final Project Close-out Amendment with AECOM/Hunt for the Stiles Avenue Widening, Underground Unforeseen Sitework Conditions, and Additional City Lot Sitework Beyond the Original Scope in the Amount of $4,593,897. (Capital Projects) | |
Strategic Priority Infrastructure | |
Description On August 13, 2020, City Council approved a contract with arena construction manager AECOM/Hunt in the total amount of $147,583,181 to execute the following projects:
Despite one of the most challenging construction environments in history, with the onset of the global pandemic resulting in labor challenges, supply-chain disruptions, and rapid escalations in material costs, the arena was completed within budget and opened by the projected hard opening date in February 2022. Much of the infrastructure projects surrounding the arena, however, encountered severe challenges, primarily caused by unforeseen below-ground conditions and obstructions, as well as impacted soils. This project close-out contract modification totaling $4,593,897 with AECOM/Hunt reflects increased costs and City-requested changes associated with two of the infrastructure projects, in addition to additional services requested by the City outside the project boundaries to make the former City Lot adjacent to the arena safe for the public and vehicular traffic. With the modifications, the final AECOM/Hunt costs will be about 2% above the contracted total. The three modifications are: 1. Widening of Stiles Avenue. Modification amount: $2,283,997. The original contract included the widening of Stiles Avenue from two lanes to four lanes from Gwinnett Street to the railroad tracks just north of the arena, relocating and improving utilities, adding of a median, sidewalks and bike lane, landscaping and hardscaping, pavement markings, and installation of signage to support the widening. This contract modification is needed due to constructability items, clarifications in plans and City-requested infrastructure changes to better meet future neighborhood needs, and unforeseen conditions relating to the roadwork. Increased costs are associated with:
2. Sitework surrounding Arena. Modification amount: $792,661. Multiple underground unforeseen conditions were encountered during the construction of the Arena. They are as follows:
3. Additional requested services beyond project limits. Modification amount: $1,517,239. The City Lot exterior improvements were an added scope service. The improvements are as follows:
| |
Recommendation Approval | |
Contact Cristy Lawrence, Senior Director, Capital Projects Management Department | |
Financial Impact Expenditure of $4,593,897 | |