Title 16. Authorize the City Manager to Execute a Contract for Phase 1B for the I&D Water Treatment Plant Optimization, Upgrade and Expansion Project with Hussey, Gay, Bell (LOCAL) in the Amount of $12,567,600. This will enable the City to proceed with capital improvements to the I&D Water Treatment Plant and associated water distribution infrastructure, ensuring the City of Savannah's water supply meets current and future demands as well as applicable regulatory compliance requirements (Water Resources). | |
Strategic Priority Infrastructure | |
Description This is for a contract for Phase 1B for the I&D Water Treatment Plant Optimization, Upgrade, and Expansion Project with Hussey, Gay, Bell in the amount of $12,567,600. Phase 1B was included in the original scope of the solicitation; however, its initiation was contingent upon the awarding of Phase 1A. With the work for Phase 1A now completed, the City is in a position to proceed with awarding Phase 1B. Following Phase 1A evaluations, Hussey Gay Bell, in collaboration with the City of Savannah’s project staff, has developed a comprehensive work plan aimed at increasing the capacity and enhancing the efficiency of Savannah's Industrial & Domestic Water Treatment Plant (I&D WTP) facility and water distribution systems. This proposal is designed to meet near-term water demands and lays the foundation for future, long-term I&D WTP capital improvements. HGB’s scope of services to be performed under Phase 1Binclude: (1) immediate capacity improvements to meet near-term water supply demands and regulatory requirements; (2) procurement of a construction manager at risk to lead construction efforts; (3) master planning of the long-term capital improvements for the I&D SWTP and distribution systems; and (4) development of a comprehensive financial plan and strategy to fund the near-term and long-term capital improvements.The scope of services are: I. Master Planning – Phase 1B
III. Water Treatment Plant Immediate Improvements
| |
Recommendation Approval | |
Contact Ronald Feldner, Chief, Water Resources | |
Financial Impact Expenditure of $12,567,600 from the Capital Improvement Fund | |
Review Comments | |
Attachments Exhibit 1: Funding Verification - I&D Plant Optimization.pdf Exhibit 2: Purchasing Notes - I&D Plant Optimization.pdf |
|