Previous Item Print Next Item

September 24, 2026 City Council Regular Meeting
Title
34. ​​​Authorize the City Manager to Execute Contract Modification No. 1 for the Pump Station Control Upgrades with Control Instruments, Inc. in the Amount of $198,283.51. (Stormwater Management)
Strategic Priority
GOAL 4:  Develop World Class Livable Environment & Infrastructure
Description

This is Contract Modification No.1 for Pump Station Control Upgrades in the amount of $198,283.51 with Control Instruments, Inc. 
 
The electronic controls that previously autonomously operated the flood control pumps at the City’s Lathrop Avenue, Fell Street, Springfield and Kayton stormwater pumping stations were originally installed between 1977 and 2003. These Programmable Logic Controllers or PLCs and their associated SCADA (Supervisory Control and Data Acquisition) software are at the end of their useful life, as repair/replacement parts and software support are non-existent. Stormwater Management Department staff have been working on the replacement of these controls to ensure flood control is maintained for the City of Savannah.  Additional work needed for these critical facilities includes generator status data integration, remote monitoring integration, and fuel tank level sensor integration. 
 
By awarding Control Instruments, Inc. the change order for this work, the City’s stormwater pumping stations will have the same controls, SCADA software, and computers. This will enable the control of all stormwater pumping stations from a single station or even remotely from a smartphone application. 

This contract was originally approved by Council on July 14, 2022, for the amount of $1,419,287.00.  The total amount of this contract to date, including this modification, is $1,617,570.51.

Delivery: As needed. Terms: Net 30 days. The vendor is:

S.S. Control Instruments, Inc. (Smyrna, GA) (D) $198,283.51

A pre-bid meeting was not conducted, as this is a sole source. (D) Indicates a Non-local, non-DBE business.   

Recommendation

Approval

Contact
Zack Hoffman, Senior Director, Stormwater Operations
Financial Impact
Expenditure of $198,283.51 from Capital Improvement Fund
Review Comments
Attachments
Exhibit 1: Funding Verification - Contract Modification No. 1 for the Pump Station Control Upgrades.pdf
Exhibit 2: Purchasing Notes - Contract Modification No. 1 for the Pump Station Control Upgrades.pdf