19. Authorize the City Manager to Execute a Contract for Chlorine Tank Hoist Replacement with Kone Cranes in an Amount Not to Exceed $51,912. The hoist will be used to offload both empty and full one-ton chlorine cylinders for disinfecting wastewater at the Water Reclamation Plant. (Water Reclamation)
Strategic Priority
Infrastructure
Description

This contract is to procure a chlorine tank hoist replacement from Kone Cranes in an amount not to exceed $51,912. The chlorine tank hoist will be replaced at the President Street Plant. The crane offloads both empty and full one-ton chlorine cylinders for disinfecting wastewater. The crane has been in operation since 1994 and undergoes annual reviews and inspections. However, the current system has reached the end of its duty cycle, and individual components have started to fail. These parts are not readily available and have extensive lead times. Replacing the hoist will extend its lifespan and incorporate modern features and technologies by retrofitting the hoisting units, thereby enhancing safety. One significant upgrade will include wireless control capabilities, allowing the operator to safely manage the hoist from a distance while handling loads. The retrofitted unit will also support compliance with the Department of Water Reclamation risk management plan for chlorine storage and handling. 

 

Per Division 10 section 2-4152 of the City’s Purchasing Ordinance, the City may purchase goods or services through the use of a piggyback contract. The contract used for this procurement is Arlington County contract #22-DES-ITB-451 which expires November 30, 2024. ​Delivery: As needed. Terms: Net 30 days.

 

The vendor is:  
​P.B. Kone Cranes (Arlington,VA)(D)         $51,912 

​A pre-bid meeting was not conducted as this is a piggyback contract. (D) Indicates a non-local, non-DBE business. 

Local vendors notified via the supplier portal: No

Total sent: 1

Total received: 1

Recommendation

Approval

Contact
Jacelyn Crumley, Director, Water Reclamation Department
Financial Impact
Expenditure of $51,912 from the Water Sewer Fund​