11. Motion to Authorize the City Manager to Execute Contract Modification No. 1 with Johnson-Laux Construction for the Atwood Park Construction in the Amount of $15,917.40 (Event No. 7247)
Strategic Priority
Neighborhood Revitalization
Description

Motion to authorize the City Manager to execute Contract Modification No. 1 with Johnson-Laux Construction for the Atwood Park Construction in the amount of $15,917.40.

The original contract represents the construction services for a new park located at the corner of Chatham Street and Atwood Street including a new basketball court, sidewalks, landscaping, and handicap accessible parking.  This contract modification is needed for various cost increases due to unforeseen construction conditions and minor scope changes.   These increases include the following:

  • Add for site drainage improvements
  • Add for soil stabilization detail
  • Add for tree removal

The original contract was approved by City Council on July 2, 2019 in the amount of $241,286.46.  The total amount of this contract to date including this modification is $257,203.86.   

Recommendation

Approval

Contact
Cristy Lawrence, Director of the Office of Capital Projects Management
Financial Impact
Expenditure of $15,917.40 from the Capital Improvements Fund, supported by SPLOST VI (District 4)