Title
27. Approval of Contract Amendment No. 6 for Extended Construction Administration Services for the FIS Facility Project with RS&H in the amount of $51,525.55
Strategic Priority
Good Government
Description

The FIS Facility Project exceeded its original completion date by approximately eight (8) months which required extended construction administration services. RS&H provided extended support for reviewal of submittals, coordination with Customs Border Protection on scope changes to the Facility, City of Savannah requests for additional as-built information for private components of the project and submission of additional drawings and specifications for the access control security component of the building.

 

 

Recommendation

Approval

Contact
Mr. Dawoud Stevenson, Director of Program Management
Financial Impact
Expenditure of $51,525.55 from Savannah Airport Commission Funds