Title 15. Authorize the City Manager to Execute a Contract for the Construction of a New Force Main to Serve Lift Station 166 with BRW Construction Group, LLC in the Amount of $5,971,495. The current 8” force main was built to serve only the initial phases of development and is undersized to serve the area as it approaches full development. (Public Works) | |
Strategic Priority Infrastructure | |
Description This is for a construction contract to BRW Construction Group, LLC to build a new 16” diameter force main to serve lift station #166 which serves the Highlands Boulevard/Godley Station Area. Lift Station #166 is in the Crossroads Wastewater Plant service area. The current 8” forcemain was built to serve only the initial phases of development and is undersized to serve the area as it approaches full development. The new main will be installed by a combination of the open trench, horizontal directional drill, and jack and bore methods and will be approximately 10,400 feet long.
Delivery: As needed. Terms: Net 30 days.
The vendor is: L.B. BRW Construction Group, LLC (Garden City, GA)(D) $5,971,495 2. C.A. Murren & Sons Heavy Civil, LLC (Savannah, GA)(B) $6,787,740 3. Astra Grading & Pipe, LLC (Savannah, GA)(B) $7,900,000 (B) indicates a local, non-DBE owned business, (D) indicates a non-local, non-DBE owned business | |
Recommendation Approval | |
Contact Heath Lloyd, Assistant City Manager and Chief, Infrastructure & Development | |
Financial Impact Expenditure of $5,971,495 from the Capital Improvement Fund. | |
Review Comments | |