Previous Item Print Next Item

July 19, 2018, City Council Regular Meeting
Title
21. Motion to Award Construction Contract for East Savannah Waterline Replacement to Southern Champion Construction, Inc. (Event No. 6106)
Strategic Priority
Infrastructure
Description

Recommend approval to award a construction contract for the East Savannah waterline replacement project to Southern Champion Construction, Inc. in the amount of $771,320.00. The services will be used by the Public Works and Water Resources Department to install approximately 8,400 linear feet of 6-inch-diameter waterline in the East Savannah neighborhood, located in Aldermanic District 3. Five vendors were pre-qualified to bid on this project; three of those five submitted bids.

This project included a DBE goal of 18%. The recommended bidder submitted DBE participation in the amount of 18% using Frankie Thompson Enterprise.

Recommendation

Approval

Contact
Heath Lloyd, Chief Officer of Infrastructure and Development
Financial Impact
$771,320.00 expenditure from the Capital Improvements Fund
Review Comments
Attachments
E Savannah Waterline Purchasing Summary.pdf
E Savannah Waterline Funding Verification.pdf
E Savannah Waterline Bid Tab.pdf