22. Notification of Emergency Repair of 48-Inch Pipeline by BRW Construction (Event No. 6330)
Strategic Priority
Infrastructure
Description

Notification of an emergency repair of a 48-inch Industrial and Domestic pipeline by BRW Construction in the amount of $69,728.91. A leak was caused by a defect in the pipeline near a berm, foam line, and fence owned by Colonial Oil. This infrastructure was removed and replaced so that the leak could be repaired. This vendor was the first immediately available to respond and had the necessary experience to perform the work. 

Recommendation

Approval

Contact
Heath Lloyd, Chief Officer of Infrastructure and Development
Financial Impact
$69,728.91 expenditure from the Industrial and Domestic Fund