Title 26. Authorize the City Manager to Execute a Contract for New Lift Station and Force Main with BRW Construction Group, LLC in the amount of $14,553,454.The Scope of Work Includes the Construction of Approximately 6,500 Linear Feet of 30-Inch Force Main along Pipemaker’s Canal Right of Way, from Dean Forest Road to the Travis Field Water Reclamation Facility. (Public Works and Water Resources) | |
Strategic Priority Infrastructure | |
Description This is for a New Lift Station and Force Main with BRW Construction, LLC in the amount of $14,553,454 The scope of work includes the construction of approximately 6,500 linear feet of 30-inch force main along Pipemaker’s Canal Right of Way, from Dean Forest Road to the Travis Field Water Reclamation Facility. The scope also includes the construction of a new lift station located along Pine Meadow Drive within the Chatham County Megasite. Task 2/3 “New Lift Station and Force Main to Travis Field WRF” project is a continuation of the multi-phased water and sewer improvements for Southwest Quad /New Hampstead area (Aldermanic District 5) as related to the continuous residential, commercial, and industrial growth.
L.B. BRW Construction Group, LLC (Garden City, GA)(D) $14,553,454 Ruby Collins, Inc (Smyrna, GA)(D) $17,740,365
A pre-bid conference was conducted. Local Available: No | |
Recommendation Approval | |
Contact James Laplander, Senior Director of Public Works and Water Resources | |
Financial Impact Expenditure of $14,553,454 from the Capital Improvement Fund | |