Title
26. Authorize the City Manager to Execute a Contract for New Lift Station and Force Main with BRW Construction Group, LLC in the amount of $14,553,454.The Scope of Work Includes the Construction of Approximately 6,500 Linear Feet of 30-Inch Force Main along Pipemaker’s Canal Right of Way, from Dean Forest Road to the Travis Field Water Reclamation Facility. (Public Works and Water Resources)
Strategic Priority
GOAL 4:  Develop World Class Livable Environment & Infrastructure
Description

This is for a New Lift Station and Force Main with BRW Construction, LLC in the amount of $14,553,454

The scope of work includes the construction of approximately 6,500 linear feet of 30-inch force main along Pipemaker’s Canal Right of Way, from Dean Forest Road to the Travis Field Water Reclamation Facility. The scope also includes the construction of a new lift station located along Pine Meadow Drive within the Chatham County Megasite. Task 2/3 “New Lift Station and Force Main to Travis Field WRF” project is a continuation of the multi-phased water and sewer improvements for Southwest Quad /New Hampstead area (Aldermanic District 5) as related to the continuous residential, commercial, and industrial growth.

 

L.B. BRW Construction Group, LLC (Garden City, GA)(D)      $14,553,454

       Ruby Collins, Inc (Smyrna, GA)(D)                                   $17,740,365

 

A pre-bid conference was conducted.
 

Local Available: No
Total Sent: 414
Total Received: 2

 

Recommendation

Approval

Contact
James Laplander, Senior Director of Public Works and Water Resources
Financial Impact
Expenditure of $14,553,454 from the Capital Improvement Fund