29. Approval of Change Order No. 4 with Iugis Construction, Inc. for the Terminal Concourse Expansion Project, in the Amount of $3,242,738.
Strategic Priority
N/A
Description

This change order includes all labor, equipment, and materials required to complete this work for the Terminal Concourse Expansion Project. These items include the redevelopment of the existing TSA checkpoint area from Savannah Square to Hold room No. 4, along with the addition of three breach control lanes. Other additional items include reconfiguration of the existing 18-inch storm line to accommodate the sewer tap; modification of a dry pipe valve for apron-level sprinklers; replacement of fire suppression backflow preventer in the Central Plant; upgrading the fire alarm panel from EST3 to EST4 as the EST3 system reached its end of life; infrastructure upgrades to support PC Air units on the new jet bridges; and installation of additional 4-inch thermal expansion loops for the hot-water system. SAC Job ID 30565. The individual change order items and costs are as follows:

1.   Sewer Tap Relocation (18” Ductile Pipe) = $42,590.40

2.   Fire Suppression System Relocation = $34,923.30

3.   New Backflow Preventer – Fire Suppression System (Central Plant) = $136,200

4.   Electrical Upgrades for New PC Air Units = $56,564.05

5.   Fire Alarm Panel Upgrade (EST 3 to EST 4) = $29,484.00

6.   Pedestrian Breach Control and Tenant Related Buildout = $2,904,888.04

7.   Thermal Expansion Loops and Compensator – 4 inch line = $38,087.62

Recommendation

Approval.

Contact
Mr. Dawoud Stevenson, Director, Program Management.
Financial Impact
Expenditure of $3,242,738 from Savannah Airport Commission Funds.