Previous Item | Next Item |
|
|
February 22, 2024, City Council Regular Meeting | |
Title 19. Authorize the City Manager to Execute a Construction Contract for Lift Station #193 Force Main Upgrade with Ruby-Collins Inc. in the Amount of $12,845,666. This will provide the installation approximately 26,000 linear feet of 24" sewer forcemain to convey flow from lift station #193 the west side of I-95/Chatham County Megasite. (Public Works & Water Resources) | |
Strategic Priority Infrastructure | |
Description This is for a construction contract for Lift Station #193 force main upgrade with Ruby-Collins Inc. in the total amount of $12,845,666. This will provide the installation of approximately 26,000 linear feet of 24-inch sewer force main to convey flow from Lift Station #193 on the west side of I-95/ Chatham County Megasite. Installation of the proposed force main will address short-term sewage conveyance capacity shortfalls for South West Quadrant and is a part of multi-phased water and sewer improvements to sustain rapid residential, commercial, and industrial development.
Local vendors notified via the supplier portal: Yes Total sent: 728 Total received: 2 | |
Recommendation Approval | |
Contact James Laplander, Director, Public Works & Water Resources | |
Financial Impact Expenditure of $12,845,665.60 from the Capital Improvement Fund | |
Review Comments | |
Attachments Exhibit 1: Funding Verification - LS 193.pdf Exhibit 2: Purchasing Notes - LS 193.pdf |
|