Title 14. Authorize the City Manager to Execute Contract Modification No. 1 for Lift Station No. 23 Repairs with Astra Grading and Pipe, LLC in the Amount of $501,270. The increased cost was due to needing an additional 354 linear feet of pipe for the project, the addition of a retaining wall to support the generator pad on the side slope, and upgrading electrical strips from copper to silver plating for increased life. (Public Works & Water Resources) | |
Strategic Priority Infrastructure | |
Description This is contract modification no. 1 for Lift Station No. 23 repairs with Astra Grading and Pipe, LLC in the amount of $501,270. Lift Station No. 23 serves the West Savannah and the Chatham Parkway corridor, pumping millions of gallons of untreated sewage east across historic downtown from the foot of the Talmadge Bridge to the President Street Treatment Plant. The increased cost was due to the omission of 354 linear feet of pipe from the project, the addition of a retaining wall to support the generator pad on the side slope, and upgrading electrical strips (busbars) from copper to silver plating for increased life.
This contract was originally approved by the Council on December 21, 2021, in the amount of $19,273,000. The total amount of this contract to date, including this modification is $19,774,269.99. | |
Recommendation Approval | |
Contact Jim Laplander, Director, Public Works & Water Resources Division | |
Financial Impact Expenditure of $501,270 from the Capital Improvement Fund | |
Review Comments | |
Attachments Exhibit 1: Funding Verification - Lift Station 23.pdf Exhibit 2: Purchasing Notes - Lift Station 23.pdf |
|