August 27, 2026 City Council Regular Meeting
Title
53. Approval of Task Work Order No. 25 with AECOM for Design Services for the Lifecycle Replacement of Air Handler Units and Fan Coil Units, in the Amount of $54,000
Strategic Priority
N/A
Description

The original air handling units (AHUs), installed in 1994, have reached the end of their service life and require replacement. This project is Phase 3 of the replacement project of AHUs originally installed in 1994. AECOM has engaged Chatham Engineering to support this project. AECOM will coordinate with Chatham Engineering and provide engineering services, including design and bidding phase administration, for the replacement of air handling units serving the concourse, central plant, apron-level offices, and third-floor office areas.

Recommendation

Approval

Contact
Financial Impact
Expenditure of $54,000 from Savannah Airport Commission Funds