Title 12. Authorize the City Manager to Execute a Final Closeout Modification for 2155 West Gwinnett Street, Fire Support and Code Compliance Building with Johnson-Laux Construction, LLC in the Amount of $220,330.75. This final modification is needed to cover additional costs associated with unforeseen conditions. (Capital Projects) | |
Strategic Priority Infrastructure | |
Description This is for a final closeout modification with Johnson-Laux Construction, LLC for the Fire Support and Code Compliance Building in the amount of $220,330.75. The original contract included the renovation/build-out of an existing 15,000-square-foot unfinished metal building at 2155 West Gwinnett Street for the Code Compliance Department and a supply storage facility for the Savannah Fire Department. The build-out provides offices and a meeting room, a customer service area, locker rooms/showers, a breakroom, various storage areas, and auxiliary space. The project also includes paved and gravel driveways and walkways, paved ADA parking, a second gravel parking lot, and landscaping.
The contract amendment is needed to cover additional costs including the following: • Removal and replacement of unsuitable soil.
| |
Recommendation Approval | |
Contact Cristy Lawrence, Senior Director, Capital Projects Department | |
Financial Impact Expenditure of $220,330.75 from the Capital Improvement Fund | |
Review Comments | |
Attachments Exhibit 1: Funding Verification - Fire Support Center.pdf Exhibit 2: Purchasing Notes - Fire Support Center.pdf |
|