23. Motion to Approve Contract with Mock Plumbing and Mechanical, Inc. to Replace Packaged Chiller
Strategic Priority
Infrastructure
Description

The Savannah Airport Commission recommends approval to procure services from Mock Plumbing and Mechanical, Inc. to replace packaged chiller in the amount of $69,761.00.

Mock Plumbing and Mechanical, Inc. will provide labor and material to replace the existing packaged chiller at the SAC combined maintenance facility. The replacement is a new HVAC chiller. The new chiller will include a five-year parts and labor warranty. This unit is a scheduled replacement for the existing chiller, which has reached the end of its useful lifecycle.

Bids were received through the City of Savannah’s Purchasing Department, Event No. 6384.

The following bids were received:

(B) Mock Plumbing & Mechanical                                    Savannah, GA               $69,471.00

(D) Johnson Controls                                                       N. Charleston, SC         $76,454.00

(B) Edge Air Cond. & Refrigeration                                  Pooler, GA                    $97,972.00

(D) Brooks Building Solutions                                          Jacksonville, FL             (No Bid)

(B) Daiken Applied Americas                                           Savannah, GA             $95,694.00

Recommendation

Approval

Contact
Brooks Stillwell, City Attorney
Financial Impact
Savannah Airport Commission funds in the amount of $69,761.00