Previous Item Print Next Item

September 11, 2025 City Council Regular Meeting
Title
25. Approval to Execute a Contract with Cooper Construction, for All Services Associated with the Replacement of Three Boilers, in the Amount of $918,800.
Strategic Priority
N/A
Description

Savannah Airport Commission (SAC) has issued bids (SAC 30648) for the lifecycle replacement of three (3) boilers serving the terminal facility. The existing boilers, originally installed in 1994, have reached the end of their lifecycle and have been budgeted for this replacement this year. The RFQ was publicly advertised, beginning July 14, 2025, and closed on August 19, 2025. SAC received two (2) qualified bids for consideration.  This project is a budgeted item with an allocated budget of $1,000,000.

 

(D)Cooper Construction, Vidalia, GA | $918,800

(B)Erickson Associates, Savannah, GA | $1,100,000

 

(B)Local, Non-DBE Owned Business, (D)Non-Local, Non-DBE Owned Business

Recommendation

Approved. 

Contact
Mr. Dawoud Stevenson, Director, Program Management.
Financial Impact
Expenditure of $918,000 from Savannah Airport Commission Funds.
Review Comments
Attachments

No attachments available

Agenda Plus