September 11, 2025 City Council Regular Meeting |
Title 24. Approval of Change Order No. 3 with C.W. Matthews Contracting Co., Inc. for the Taxiway G and Bridge Project, in the Amount of $51,107. |
Strategic Priority N/A |
Description
This change order provides compensation for additional equipment, labor, and materials required to remove and replace unsuitable subgrade material at the tie-in location between Taxiways G and H. The contractor will install geogrid, #57 stone, and engineered fill to replace the unsuitable soils. SAC Job ID 30620.
|
Recommendation
Approval.
|
Contact Mr. Dawoud Stevenson, Director, Program Management. |
Financial Impact Expenditure of $51,107 from Savannah Airport Commission Funds. |