Previous Item Print Next Item

October 10, 2024, City Council Regular Meeting (Postponed to October 11, 2024 at 10:30 a.m.)
Title
13. Authorize the City Manager to Execute Contract Modification No. 1 for the Replacement of a Heat Exchanger with Huber Technologies, Inc in the Amount of $15,931. The additional amount will cover the additional labor cost that will be needed to complete the installation. (Water Reclamation)
Strategic Priority
Good Government
Description

This contract modification is for the replacement of a heat exchanger with Huber Technologies, Inc. in the amount of $15,931. The existing radiator has failed due to grease and chemical degradation. The inlet radiator cools the hot air exiting the dryer, facilitating the release of moisture from the saturated air stream. Subsequently, the air stream passes through the radiator and condensing unit, resulting in cooler and drier air being returned to the dryer head for efficient drying purposes. 

 

The original quote was provided by Huber, estimating completion of the service within two days. However, during the dismantling of the inlet radiator, unforeseen issues arose, necessitating an extension of the installation period by two days. Hence, additional funds are required. This was originally approved by the City Manager on July 21, 2024, in the amount of $44,769.99. The total amount of this contract, including this modification, is $60,698.

Recommendation

Approval

Contact
Jacelyn Crumley, Director, Water Reclamation Department
Financial Impact
Expenditure of $15,931 from the Water and Sewer Fund
Review Comments
Attachments
Exhibit 1: Funding Verification - Heat Exchanger Replacement.pdf
Exhibit 2: Purchasing Notes - Heat Exchanger Replacement.pdf
Agenda Plus