Title 14. Motion to Approve Contract Modification Number 1 with E&D Contracting Services, Inc. for Colonial Drive Drainage Improvements in the amount of ($13,388.50) and Increasing the Contract Term by 127 Calendar Days (Event 6043) | |
Strategic Priority Infrastructure | |
Description Recommend approval of Contract Modification No. 1 with E&D Contracting Services, Inc. for Colonial Drive Drainage Improvements (Aldermanic District 3). This modification amounts in a reduction of $13,388.50. This project involved the replacement of 174 Linear Feet of open ditch and road crossing culvert with a 3x6 foot precast culvert. The precast culvert utilized a water tight gasket (ASTM C1677) that had not been used by the City of Savannah previously. Procurement of the new gasketed culvert required a 127 day extension to the contract. The contract price deductions were mostly due to the project being completed in one phase and not requiring undercutting and replacement. The list of deduction are: Phase 1:
Phase 2:
The original contract was approved by Council on July 19, 2018 in the amount of $359,854.00 The total amount of this contract to date, including this modification, is $346,465.50 which represents a 3.7% decrease from the original contract amount. | |
Recommendation Approval | |
Contact Cristy Lawrence, Director of the Office of Capital Projects Management | |
Financial Impact Reduction of $13,388.50 to the Capital Improvements Fund, via District 3 SPLOST VI Funds | |