Title
12. Authorize the City Manager to Execute Contract Modification No.2 for Construction Services on the Gangway Platform at Rousakis Plaza with Myrick Marine Contracting Corp in the Amount of $3,145 (Event No.6709)
Strategic Priority
Infrastructure
Description

Recommend approval of Contract Modification No. 2 with Myrick Marine Contracting Corp for construction services on the gangway platform at Rousakis Plaza in the amount of $3,145.

The original contract was for the construction of a new gangway platform for the recreational and fire dock on Rousakis Plaza which collapsed in November 2016. This modification is for the replacement of 37 additional tie-rods, which are damaged and critical to keeping the docks held together

The original contract was awarded by Council on March 28, 2019 in the amount of $472,766 and Contract Modification No. 1 was approved by Council on December 5, 2019 in the amount of $162,644.80. The total amount of the contract to date, including this Contract Modification is $638,555.80.

Recommendation

Approval 

Contact
Cristy Lawrence, Director of Capital Projects Management
Financial Impact
Expenditure of $3,145 from the Capital Improvement Fund