Previous Item | Next Item |
|
|
May 27, 2021 City Council Regular Meeting | |
Title 9. Authorize the City Manager to Execute a Construction Contract for the Purchase and Unload of the Arena Pedestrian Bridge with Johnson-Laux (Local, DBE) in the Amount of $536,309 (Event No. 8481) [See report]. A Single-Structure, 110-Foot Steel Truss Bridge will be Fabricated to Cross the Springfield Canal and will (Under a Separate Contract) Connect the Surface Lot to the Arena. | |
Strategic Priority Infrastructure | |
Description Recommend approval of Phase One of a two-phase construction contract to fabricate and unload the Arena Pedestrian Bridge with Savannah-based Johnson-Laux Construction (A) in the amount of $536,309. The steel truss bridge will be 110 feet long and 16 feet wide, and will connect the parking lot with the arena. This contract, which is the first of two phases, is with Savannah-based Johnson-Laux Construction through the State of Georgia construction services contract. In this phase, Johnson-Laux will develop the bridge superstructure design, fabricate the bridge, and deliver the bridge to the site. The second phase, which will come before Council at a later date, will include installation of the bridge foundation, bridge erection, and pouring the deck. The contract is being broken into two phases to expedite commencement of fabrication due to supply-chain issues currently being experienced. This will ensure the bridge is operational in time for the planned arena opening. The State Contract with Johnson-Laux (Contract #99999-SPD-S20160216-009) was competitively bid by the State of Georgia and awarded to Johnson-Laux Construction, LLC. Per Section 2-4154 of the City’s Purchasing Ordinance, the City may purchase goods or services through the use of a State contract. S.C. Johnson-Laux (Savannah, GA)(A) $536,309 A pre-bid meeting was not conducted as this is a State of Georgia Contract. (A) indicates Local, DBE owned business. | |
Recommendation Approval | |
Contact Cristy Lawrence, Senior Director of Capital Projects | |
Financial Impact Expenditure of $536,309 from the Capital Improvement Fund | |
Review Comments | |
Attachments Exhibit 1: Funding Verification - Arena Pedestrian Bridge.pdf Exhibit 2: Memo.pdf |
|