26. Approval to Execute Change Order No. 6 with Collins Construction, Inc. for Additional Work Related to the Terminal Security Checkpoint Expansion Project, in the Amount of $67,765.
Strategic Priority
Good Government
Description

This is for Change Order No. 6 with Collins Construction, Inc. for additional work needed related to the Terminal Security Checkpoint Expansion Project. The additional work includes replacing two overhead doors at the checkpoint, which the Savannah Airport Commission requested. One door is 28-feet and the other is eight feet in height. These replacements are necessary due to the doors reaching the end of their lifecycle and new TSA regulations that mandate solid doors.

Recommendation

Approval

Contact
Dawoud Stevenson, Director, Program Management
Financial Impact
Expenditure of $67,765 from the Savannah Airport Commission Fund