Title 31. Approval to Execute a Contract with Erickson Associates, Inc. for the Lifecycle 750-Ton Chiller Replacement Project in the Amount of $514,000 | |
Strategic Priority Good Government | |
Description The project consists of the removal and disposal of the existing Chiller No. 1, York Model YTL6M6F2CWFS, which was installed in mid-1993 and is 28-years old, as well as the equipment, parts, materials, and labor required for the installation of the new chiller unit. The budget amount of $800,000 was based on current models meeting the required chiller specifications and market conditions for both equipment and labor. The following bids were received:
(B)Erickson Associates, Inc., Savannah, GA $514,000 (B)Mock Plumbing & Mechanical, Inc. Savannah, GA $538,000 (D)Y-Delta, Inc., Statesboro, GA $704,000
(B)Local, Non-Minority (D)Non-Local, Non-Minority | |
Recommendation Approval | |
Contact Mr. Dawoud Stevenson, Director of Program Management | |
Financial Impact Expenditure of $514,000 from Savannah Airport Commission Funds | |
Review Comments | |
Attachments SAC 30609 - CHILLER IMAGE.png |
|