Previous Item | Next Item |
|
|
June 9, 2022 City Council Regular Meeting | |
Title 17. Authorize the City Manager to Execute a Contract for Underground Utility Access Monitoring Devices with Kazmier & Associates LLC in the Amount of $125,000. This equipment provides a warning in the event of sanitary sewer overflows in the City’s underground utility access monitoring devices. (Sewer Maintenance & Lift Station) | |
Strategic Priority Infrastructure | |
Description This contract is to procure Underground Utility Access Monitoring Devices with Kazmier & Associates in the amount of $125,000. The Lift Station Maintenance and Sewer Maintenance Departments will be using this equipment to communicate with the City's lift stations and sewer system. Over 250 alarm monitoring devices provide communication and monitor over 150 lift station alarm monitoring devices throughout the City sewer system. This equipment prevents sanitary sewer overflows from sewer underground utilities by giving advance warning in the event sewage levels rise.
This is a sole source procurement because this vendor manufactures all Mission equipment in the state of Georgia. Delivery: As requested. Terms: Net 30 days.
S.S. Kazmier & Associates (Alpharetta, GA)(D) $125,000 (D) Indicates non-local, non-DBE business. | |
Recommendation Approval | |
Contact Heath Lloyd, Assistant City Manager & Chief, Infrastructure and Development | |
Financial Impact Expenditure of $125,000 from the Capital Improvement Fund. | |
Review Comments | |
Attachments Exhibit 1: Funding Verification - Monitoring Devices.pdf Exhibit 2: Purchasing Note - Monitoring Devices.pdf |
|