43. Approval of Change Order No. 1 with Shamrock Concrete Construction, Inc. for the Demo Air Cargo Phase 1B Project, in the Amount of $141,986.
Strategic Priority
Good Government
Description

This non-AIP change order includes all equipment, labor, and materials necessary to construct a new parking lot at the end of Bob Harmon Road to replace the Signature Parking lot removed during Phase 1B apron extension. Additional work includes the installation of AOA security fencing and a manual gate. Upon completion of the Southeast Quadrant buildout, this will replace Gate 2. SAC Job ID 30636.

Recommendation

Approval

Contact
Mr. Dawoud Stevenson, Senior Director, Program Management
Financial Impact
Expenditure of $141,986 from the Savannah Airport Commission Funds