Previous Item Print Next Item

July 14, 2022 City Council Regular Meeting
Title
38. Authorize the City Manager to Execute a Contract for a Casey North Basin Study Model with Hussey Gay Bell (LOCAL) in the Amount of $105,000. The services will provide an updated model of multiple year rain event peak water elevations to assist development site designs and flood prevention programs. (Stormwater)
Strategic Priority
Infrastructure
Description

This contract is for a Casey North Basin Study - Model and Inundation Mapping Update with Hussey Gay Bell in the amount of $105,000. Hussey Gay Bell completed the original Casey North Basin Study in 2013. Due to Stormwater Management Model (SWMM) software updates, changes in existing conditions, new data associated with Hurricane Matthew, acquisition of updated topographic information and improvements in drainage modeling technology, and update of the existing basin hydraulic model becomes critical. The new and more accurate model will provide 2,10, 50, and 100-year rain event peak water elevations to assist development site designs and COS flood prevention programs, it will also provide drainage improvements recommendations and cost estimates.

 

This is a sole source procurement because Hussey Gay Bell completed the original model and is familiar with the basin layout.

 

S.S. Hussey Gay Bell (329 Commercial Dr suite 200 Savannah,GA)(B)             $105,000

(B) Indicates a local, non-DBE-owned business. 

Recommendation

Approval

Contact
Heath Lloyd, Assistant City Manager and Chief, Infrastructure & Development
Financial Impact
Expenditure of $105,000 from the Stormwater Management Fund.
Review Comments
Attachments
Exhibit 1: Funding Verification - Casey North Drainage Basin Study.pdf
Exhibit 2: Purchasing Notes - Casey North Drainage Basin Study.pdf