Previous Item | Next Item |
|
|
January 4, 2018 City Council Regular Meeting | |
Title Motion to Award Construction Contract for Bacon Park Bridge Replacement to Southeastern Site Development (Event No. 5543) | |
Description Recommend approval to award a construction contract to Southeastern Site Development, Inc. in the amount of $605,206.95. These services will be used to replace Service and Legends II Bridges on the Bacon Park Golf Course that were damaged during Hurricane Matthew. The Legends II Bridge is currently unusable and the Service Bridge weight capacity has been severely reduced. This project will replace both bridges with a new steel beam structure with a wood surface. The bridges have been designed to reduce future damage to them in the event of another storm. This project will include reimbursements from FEMA. This project included a DBE goal of 10%. Based on the proposed schedule of DBE participation submitted by the recommended proposer, the overall DBE participation for this project will be 10% being performed by Bly, Bly, Pittman. | |
Recommendation Approval | |
Contact Heath Lloyd, Chief Officer of Infrastructure and Development | |
Financial Impact $605,206.95 | |
Review Comments | |
Attachments Bacon Park Bridge Bid Tab.pdf Bacon Park Bridge Funding.pdf Bacon Park Bridge Purchasing Summary.pdf |
|