Title 17. Authorize the City Manager to Execute a Contract for the Design of the New Hampstead Public Safety Facility with Greenline Architecture (LOCAL)(DBE) in an Amount Not to Exceed $582,500. The consultant’s services will be used for developing and implementing design and construction documents for a 25,000+ square foot joint police and fire facility that also includes shared space for department and community use, as well as training and storage. (Capital Projects) | |
Strategic Priority Public Safety | |
Description This contract is for the design services for the New Hampstead Public Safety Facility project with Greenline Architecture in an amount not to exceed $582,500. The consultant’s services will be used for developing and implementing design and construction documents for a 25,000+ square foot joint police and fire facility that also includes shared space for department and community use, as well as training and storage. The services will include analysis of site conditions, development of a conceptual facility design, preparation of construction documents, construction administration, and project closeout. The building(s) will include enhanced protections according to critical facility standards and the site will be developed to include stormwater accommodations, driveways, parking, landscaping, and other auxiliary components.
The method used for this procurement was the request for proposals (RFP), which evaluates criteria in addition to cost. The proposals were evaluated based on qualifications and experience, methodology, references, Savannah First, and DBE participation. Four proposals were received in response to this RFP. All proposals were reviewed and fully evaluated by a selection committee of City staff.
The bidders are:
A pre-proposal meeting was conducted and five vendors attended. (A) Indicates local, DBE-owned business. (C) Indicates non-local, DBE-owned business. (D) Indicates non-local, non-DBE-owned business. Local vendors notified via the supplier portal: Yes Total sent: 400 Total received: 4 | |
Recommendation Approval | |
Contact Cristy Lawrence, Senior Director, Capital Projects Management Department | |
Financial Impact Expenditure of $582,500 from the Capital Improvement Fund | |
Review Comments | |
Attachments Exhibit 1: Funding Verification - New Hampstead Public Safety Design Services.pdf Exhibit 2: Purchasing Notes - New Hampstead Public Safety Design Services.pdf |
|