12. Motion to Authorize the City Manager to Execute Contract Modification No. 1 with Dabbs-Williams General Contractors, LLC for the Industrial and Domestic Water Laboratory in the Amount of $24,188.19 (Event No. 6047)
Strategic Priority
Infrastructure
Description

Recommend approval of Contract Modification No.1 for Industrial and Domestic Laboratory building to Dabbs-Williams General Contractors, LLC in the amount of $24,188.19.

The original contract was for the construction of the new laboratory building which will be used as a quality control testing facility for the Water Supply and Treatment Department.

This contract modification includes additional building equipment and electrical infrastructure.  It also includes a 70 day extension in order to complete necessary work.

This contract was originally approved by Council on July 19, 2018 in the amount of $2,038,000.  The total amount of this contract to date, including this modification is $2,062,188.19.

Recommendation

Approval

Contact
Heath Lloyd, Chief Infrastructure and Development Officer
Financial Impact
Expenditure of $24,188.19 from the Capital Improvements Fund, Supported by the Water and Sewer Fund and the Industrial and Domestic Water Fund