Previous Item Print Next Item

December 19, 2024, City Council Regular Meeting
Title
36. Authorize the City Manager to Execute a Contract for Two Bar Screens from Cornerstone H2O in an Amount not to exceed $1,740,000. The bar screens remove debris from the stormwater pumping stations. (Stormwater)
Strategic Priority
Infrastructure
Description

This is to procure two (2) bar screens from Cornerstone H2O in an Amount not to exceed $1,740,000.00.  The existing bar screens located at the Fell Street Pumping Station were designed and installed in 1986 and have now reached their lifespan and are required at the thirty-eight-year-old pump station. The design of the pumping stations will only accept Veola climber bar screens that will work for the application.  The bar screens are critical components for the pumping stations to remove debris from the pumped canal waters and will trap the debris to create a dam preventing stormwater pumping. This is a sole source purchase because this vendor is the only regional distributor of Veola screens and is compatible with the existing pumping station. Delivery: As Needed. Terms: Net 30 Days. The vendor is:   


S.S.      Cornerstone H2O (Peachtree City, GA)(D)   $1,740,000.00 

(D)Indicates Non-Local, Non-DBE Business.

Recommendation

Approval

Contact
Zack Hoffman, Director, Stormwater Management Division
Financial Impact
Expenditure of $1,740,000.00 from the Capital Improvement Fund
Review Comments
Attachments
Exhibit 1: Funding Verification - Fell St Bar Screens.pdf