47. Approval of Change Order No. 7 with Iugis Construction, Inc. for the Terminal Concourse Expansion Project, in the Amount of $365,112
Strategic Priority
N/A
Description

This Change Order includes the additional equipment, labor, and materials required to remove and restripe all gates and service road markings on the carrier apron, extend a fresh air intake, install a new fire pump disconnect, install condensate pumps, install two new access doors to the plumbing chase located behind the men’s and women’s restrooms, switching the railings along the ramp in the new pedestrian breach area from painted metal to stainless steel, and removing the proposed photocell and tying into the existing one for the newly installed apron lights.

 

• Concourse Gate Restriping - $290,835

• Extend Fresh Air Intake - $12,111.63

• Fire Pump Disconnect - $31,259.45

• Condensate Pumps & Drains For FCUs - $4,597.36

• Install Two Chase Doors - $6,795.60

• Material Change For Railings - $9,075

• Photocell Relocation - $10,437.85

Recommendation

Approval

Contact
Financial Impact
Expenditure of $356,112 from Savannah Airport Commission Funds