Previous Item | Next Item |
|
|
August 27, 2020 City Council Meeting | |
Title 15. Authorize the City Manager to Execute a Contract for Engineering Design and Construction Overview Services with Hussey, Gay, Bell, and DeYoung, Inc. for up to $356,990 (Event No. 7867) | |
Strategic Priority Infrastructure | |
Description Recommend approval to award a contract for engineering design and construction overview services for improvements to Lift Station #166 to Hussey, Gay, Bell, and DeYoung, Inc. for up to $356,990. The Water and Sewer Planning and Engineering Department will use these services for the design of a new sanitary sewer forcemain to serve the existing Lift Station #166, which serves the Godley West service area, north of the airport and west of I-95. The existing lift station design included an 8” forcemain to be built to serve the initial development in the area. The service area has matured and a second parallel forcemain is now required so that the pumps can keep pace with the increased flow of sanitary sewer. | |
Recommendation Approval | |
Contact Chuck Tessmer, Director of Water & Sewer, Planning & Engineering | |
Financial Impact Expenditure of $356,990 from the Capital Improvement Fund | |
Review Comments | |
Attachments Exhibit 1: Purchasing Summary - Engineering Design and Construction Overview Services.pdf Exhibit 2: Funding Verification - Engineering Design and Construction Overview Services.pdf |
|