20. Approval to Procure Airfield Lighting Cable from CED, in the Amount of $29,600.
Strategic Priority
Good Government
Description

This procurement is for 40,000 ft of FAA-certified L-824 underground electrical cable for airport lighting circuits. This cable is needed for the taxiway LED lighting project approved at the September 2024 Commission Meeting. The lead time is four (4) weeks.

 

The following bids were received:

(B)CED-Savannah, Savannah, GA | $29,600
(D)Airside Solutions, Auburn, WA | Non-responsive

(B)Local, Non-Minority (D)Non-Local, Non-Minority

Recommendation

Approval

Contact
Dawoud Stevenson, Director, Program Management
Financial Impact
Expenditure of $29,600 from the Savannah Airport Commission Fund