Previous Item Print Next Item

November 25, 2025 City Council Meeting
Title
27. Approval to Execute Change Order No. 11 for the Terminal Security Checkpoint Expansion Project with Collins Construction, Inc., in the Amount of $154,634.
Strategic Priority
N/A
Description

This change order is a result of multiple challenges faced by Collins Construction, which led to additional costs beyond their control during the project’s construction, including extended fabrication times for the emergency generator, automated transfer switch, and control device. Labor cost involved and time lost operating the crane ocurred while waiting for modifications to the FAA Height Restriction Permit. SAC Job ID 30566. 

Recommendation

Approval.

Contact
Mr. Dawoud Stevenson, Sr. Director, Program Management.
Financial Impact
Expenditure of $154,634 from Savannah Airport Commission Funds.
Review Comments
Attachments

No attachments available

Agenda Plus