32. Approval to Execute a Contract with AT&T for the Demo Air Cargo Phase 2 Project, in an Amount Not to Exceed $150,000
Strategic Priority
N/A
Description

This contract provides for the removal of existing overhead AT&T copper and fiber communication lines along Bob Harmon Road and Nicholson Drive and their replacement with equivalent underground communication lines to maintain service to Signature, leased hangars, and other airport tenants in the area. This work is required to facilitate the extension of the General Aviation apron as part of the Demo Air Cargo Phase 2 project. These expenses are eligible for AIP reimbursement. SAC Job ID 30650.

Recommendation

Approval

Contact
Dawoud Stevenson Senior Director of Program Management
Financial Impact
Expenditure of $150,000 from Savannah Airport Commission Funds