Title 27. Authorized the City Manager to Execute a Contract for the Removal of Emergent Aquatic Vegetation with MPW Construction, LLC (LOCAL)(DBE) in the Amount of $1,300,000. The alum sludge pond is located on-site at the Industrial & Domestic water treatment facility and is roughly 10 acres in size. (Industrial & Domestic Water Plant) | |
Strategic Priority Infrastructure | |
Description This contract is for the procurement of removal of emergent aquatic vegetation services at the Industrial & Domestic (I&D) Water Treatment Facility (WTF) by MPW Construction, LLC in the amount of $1,300,000. The alum sludge pond is located on-site at the I&D WTF and is roughly 10 acres in size. The alum sludge pond is a holding location for spent process water from the potable water treatment operation. By spending time in the alum sludge pond, the processed water has an opportunity to settle out accumulated debris before it is discharged into the environment. The Georgia Department of Environmental Protection (GA EPD) regulates the quality of the discharge water from the alum sludge pond. Routine maintenance on the alum sludge pond is required to ensure it functions as intended and produces discharge water that meets GA EPD’s water quality requirements. The last maintenance activities, which included alum sludge dredging from the pond, occurred in 2017. Since then, large amounts of vegetation have accumulated that need to be removed before additional dredging activities can take place.
The method used for this procurement was the competitive bid wherein an award is made to the lowest responsive, responsible bidder. Terms: Net 30 days. Delivery: As requested.
The bidders are: 02. Ruby-Collins, Inc. (Smyrna, GA)(D) $1,989,379 03. Merrell Bros., Inc. (Kokomo, IN)(D) $4,197,350
A pre-proposal meeting was conducted and 11 vendors attended. (A) Indicates local owned DBE business. (D) Indicates non-local, non-DBE-business. Local vendors notified via the supplier portal: Yes Total sent: 572 Total received: 3 | |
Recommendation Approval | |
Contact Bryan Shaw, Director, Supply and Treatment Division | |
Financial Impact Expenditure of $1,300,000 from the I & D Water Plant Fund | |
Review Comments | |
Attachments Exhibit 1: Funding Verification - Alum Sludge Pond Vegetation Removal.pdf Exhibit 2: Purchasing Notes - Alum Sludge Pond Vegetation Removal.pdf |
|