May 22, 2025 City Council Regular Meeting |
Title 35. Approval of Change Order No. 4 with Collins Construction for the Fuel Storage Facility Expansion Project, in an Amount NTE $420,265. |
Strategic Priority Good Government |
Description
This change order includes the additional equipment, labor, and materials required to install a high-level shutoff valve for Storage Tank 2. Due to the small diameter of the existing tank filling nozzle, an internal high-level control valve cannot be accommodated. As a result, a top-mounted external solution is necessary. Additionally, this change order replaces the two existing fuel loading and offloading pumps with newer more efficient pumps. SAC will apply for reimbursement of this work upon close out of the grant. SAC Job ID 30619.
|
Recommendation
Approval
|
Contact Mr. Dawoud Stevenson, Sr. Director, Program Management |
Financial Impact Expenditure in an amount NTE $420,265 from Savannah Airport Commission Funds |