37. Approval of Change Order No. 3 with EE Reed Construction for Design Modifications to Building 2, the Air Cargo Facility, in the Amount of $1,605,000.
Strategic Priority
Good Government
Description

Change Order No. 3 accounts for the additional materials and labor required to re-design Building 2, as requested by UPS. These changes were requested after construction of the Air Cargo facility had begun.  These changes were necessitated because UPS requested relocation from the east side of Building 2 to the west side. Changes to the building include but are not limited to the loading docks, electrical, overhead doors, plumbing, enlarged cargo apron, and site work. The requested changes are necessary to help facilitate their company operations. 

Recommendation

Approval

Contact
Mr. Dawoud Stevenson, Sr. Director, Program Management
Financial Impact
Expenditure of $1,605,000 from Savannah Airport Commission Funds