Previous Item | Next Item |
|
|
March 14, 2024, City Council Regular Meeting | |
Title 19. Authorize the City Manager to Execute a Contract for Supervisory Control and Data Acquisition (SCADA) Upgrade with Control Instruments, Inc. in an Amount Not to Exceed $684,385. The upgrade will include an overhaul for the 29-year-old system and is needed because the components of the Programmable Logic Controls (PLC) are obsolete and replacement parts are difficult to find. (Water Reclamation) | |
Strategic Priority Infrastructure | |
Description This contract is to procure a supervisory control and data acquisition (SCADA) upgrade with Control Instruments, Inc. in an amount not to exceed $684,385. The Water Reclamation Plant SCADA system has been in place for over 29 years and must be upgraded because the components of the Programmable Logic Controls (PLC) are obsolete and replacement parts are difficult to find. The SCADA system is a system of software and hardware elements that maintains efficiency in the City’s Public Works and Water Resource functions by controlling processes locally or at remote locations; monitors, gathers, and processes real-time data; directly interacts with devices such as sensors, valves, pumps, and motors, and; records events into a log file.
The scope of work will allow the new system to be built and factory-tested on new servers and workstations. Once the testing has been completed, the systems will be installed onsite in parallel to the existing Emerson System and replaced with industry-standard Rockwell Automation Programmable Logic Controls (PLCs). Additionally, the use of the new system provides an opportunity to improve efficiency and productivity. The bid was advertised, opened, and reviewed. Delivery: As needed. Terms: Net 30 days.
The vendor is: L.B. Control Instruments, Inc. (Smyrna, GA)(D) $684,385 0.2 Silver Lake Systems & Design (Rincon, GA)(D) $1,519,856.42
A pre-bid meeting was conducted. (D) Indicates a non-local, non-DBE-owned business. Local vendors notified via supplier portal: Yes Total Sent: 632 Total received: 2 | |
Recommendation Approval | |
Contact Jacelyn Crumley, Director, Water Reclamation Division | |
Financial Impact Expenditure of $684,385 from the Water & Sewer Fund | |
Review Comments | |
Attachments Exhibit 1: Funding Verification - Water Reclamation SCADA Upgrade.pdf Exhibit 2: Purchasing Note - Water Reclamation SCADA Upgrade.pdf |
|