61. Motion to Authorize the City Manager to Execute Contract Amendment No. 3 for Springfield Basin in the Amount of $111,420 (Event No. 5381)
Strategic Priority
Infrastructure
Description

Recommend approval of Contract Amendment No. 3 for the Springfield Basin Model Calibration contract with Thomas & Hutton Engineering in the amount of $111,420.

The original contract was for the updating of the City’s Springfield Canal basin hydraulic model. This was a sole source because Thomas & Hutton Engineering exclusively has performed the modeling of the basin. Therefore, additional design by this vendor did not require duplication of design work. This amendment is needed to continue the building of Springfield Canal/Basin model by refining the basin boundaries and drainage infrastructure.  An additional study will potentially provide Community Rating System points toward lowering the rating and providing a greater discount on flood insurance premiums.

The original contract was approved by Council on August 3, 2017 in the amount of $82,500.00.  The total contract amount to date, including this modification, is $248,550. 

Recommendation

Approval

Contact
Heath Lloyd, Chief Infrastructure and Development Officer
Financial Impact
$111,420.00 expenditure from the Capital Improvements Fund