21. Approval to Execute a Construction Contract with C.W. Matthews Contracting Co. Inc. for the Taxiway G and Bridge Project, in the Amount of $15,732,000.
Strategic Priority
Good Government
Description

This contract is for construction services. The project involves constructing Taxiway H and a bridge across Gulfstream Road, which will serve as a parallel taxiway to the air cargo area. The project will be Passenger Facility Charge (PFC) and Airport Improvement Program (AIP) funded and is an approved 2024 budget item.

 

The bidders are:

(D)C.W. Matthews Contracting Co. Inc., Marietta, GA | $15,732,000

(D)Reeves Construction Company, Garden City, GA | $16,954,583

 

(D)Non-Local, Non-Minority.

Recommendation

Approval

Contact
Dawoud Stevenson, Director, Program Management
Financial Impact
Expenditure of $15,732,000 from the Savannah Airport Commission Fund