Previous Item Print Next Item

July 10, 2025 City Council Regular Meeting
Title
37. Approval to Execute a Contract with Arentz General Contracting for Construction Services Associated with the Maintenance Equipment Storage Building Project, in the Amount of $495,000.
Strategic Priority
Good Government
Description

This project includes the construction of a 10-bay maintenance equipment storage building, a concrete access apron, storm drainage modifications, and the installation of security fencing.  The new shed bays will match the size and clearance of the existing shed bays on the north side of the maintenance complex. SAC Job ID 30643.

 

(B)Arentz General Contracting, Savannah, GA | $495,000

(B)Griffin Contracting, Inc., Pooler, GA | $598,547

(B)Johnson-Laux Construction, LLC, Savannah, GA | $638,980

(D)Salacia Construction, LLC, Ridgeland, SC | $649,290

(E)Collins Construction Services, Inc., Savannah, GA | $949,000

 

(B)Local, Non-Minority, (D)Non-Local, Non-Minority, (E)Local, Woman Owned Business

Recommendation

Approval.

Contact
Mr. Dawoud Stevenson, Director, Program Management.
Financial Impact
Expenditure of $495,000 from Savannah Airport Commission Funds.