July 10, 2025 City Council Regular Meeting |
Title 34. Approval of Change Order No. 3 with Lugis Construction, Inc. for the Terminal Concourse Expansion Project, in the Amount of $294,507. |
Strategic Priority Good Government |
Description
This change order includes the additional equipment, labor, and materials necessary for the installation of Terrazzo flooring in the concourse bathrooms, the addition of double duplex floor and wall outlets, the replacement of two light poles, and the demolition and replacement of terminal apron concrete that was not included in the original scope. SAC will submit for reimbursement at project closeout. SAC Job ID 30565.
|
Recommendation
Approval
|
Contact Mr. Dawoud Stevenson, Director, Program Management |
Financial Impact Expenditure of $294,507 from Savannah Airport Commission Funds |