January 12, 2023 City Council Regular Meeting |
Title 29. Approval to Execute Change Order No. 1 for the Terminal Security Checkpoint Expansion Project with Collins Constructions, Inc., in the Amount of $2,754,258.59. |
Strategic Priority Good Government |
Description
This change order will develop the lower level within the footprint of the checkpoint buildout into a leasable office and storage space. This space was requested by the airlines, ground handling, and Host to support their operations. This space is ineligible for federal funding.
|
Recommendation
Approval
|
Contact Dawoud Stevenson, Director, Program Management/IT |
Financial Impact Expenditure of $2,754,258.59 from Savannah Airport Commission Funds |