The Savannah Airport Commission requests approval of an emergency purchase related to the Transportation Security Administration’s additional security lane contractor costs with K2 Construction Consultants, Inc., in the amount of $38,593.25.

At the March 1, 2017, Commission meeting, staff recommended approval to act on an emergency purchase related to the expansion and relocation of equipment at the Transportation Security Administration security checkpoint. Staff received quotes from two bidders on Wednesday, March 1, 2017. The scope of work required relocating three Smiths X-Ray units, two walk-through metal detectors, and one L3 Advance Imaging Technology unit, between 3 and 12 feet to accommodate a fourth lane at the Transportation Security Administration checkpoint. The work was required to be performed by a Transportation Security Administration approved contractor. The following quotes were received:

Low bidder:

(D) K2 Construction Consultants, Inc.              Bethesda, MD             $38,593.25

(D) Leidos Innovations Corporation                  Gaithersburg, MD       $59,321.07     

 

Recommendation

Approval

Contact
Brooks Stillwell, City Attorney
Financial Impact
Airport funding: $38,593.25